A 40-unit pro forma. Return on cost 3.72 percent against a 6.50 percent hurdle.
One building, underwritten at D.C. market inputs. Every figure below comes from the calculator at the end of this page.
1. Program
| Units | Net SF | Rent / mo | |
|---|---|---|---|
| Studio | 10 | 484 | $1,821 |
| One-bedroom | 22 | 697 | $2,302 |
| Two-bedroom | 8 | 996 | $3,090 |
| Total | 40 | 28,142 | $2,450 avg |
Efficiency 80 percent. Gross building area 35,178 SF.
2. Development budget
| Line | Basis | Total | Per unit | Share |
|---|---|---|---|---|
| Land | estimate | $2,400,000 | $60,000 | 14.7% |
| Hard cost | $275 / gross SF | $9,673,812 | $241,845 | 59.2% |
| Parking | 20 spaces × $35,000 | $700,000 | $17,500 | 4.3% |
| Soft cost | 20% × (land + hard + parking) | $2,554,762 | $63,869 | 15.6% |
| Entitlement carry | land × 8% × 14/12 | $224,000 | $5,600 | 1.4% |
| Construction carry | (hard + parking + soft) × 50% × 8% × 18/12 | $775,715 | $19,393 | 4.8% |
| Total development cost | $16,328,290 | $408,207 | 100% |
Entitlement carry runs on land only. The building is not financed until construction starts.
Construction carry uses the average drawn balance. The loan funds in over 18 months, so on average half is outstanding.
3. Stabilized operations
| Line | Basis | Annual |
|---|---|---|
| Gross potential rent | 40 × $2,450 × 12 | $1,176,000 |
| Inclusionary zoning discount | 4 units × ($2,450 − $1,550) × 12 | −$43,200 |
| Other income | +3% | +$33,984 |
| Vacancy and credit loss | −7% | −$81,675 |
| Effective gross income | $1,085,109 | |
| Operating expenses | $9,500 / unit | −$380,000 |
| Property tax | 0.85% of value | −$98,253 |
| Net operating income (NOI) | $606,856 |
Expense ratio 44 percent of income.
Tax is circular. It is charged on value, and value depends on NOI after tax. Solved directly:
NOI = (EGI − opex) ÷ (1 + tax rate ÷ cap rate) = $705,109 ÷ 1.162 = $606,856
4. Value and return
Value = NOI ÷ cap rate = $606,856 ÷ 5.25% = $11,559,166
Value − cost = −$4,769,124
Return on cost = NOI ÷ cost = 3.72%
Hurdle = cap rate + developer spread = 5.25% + 1.25% = 6.50%
Gap = 278 bps
The spread is the premium for construction and lease-up risk over buying a finished asset at the cap rate.
5. Lever attribution
Each lever run alone against base. The package runs all zoning reforms together.
| Lever | Return on cost | Change | Share of gap |
|---|---|---|---|
| Base | 3.72% | ||
| Entitlement 14 → 4 months | 3.75% | +4 bps | 1% |
| No parking minimum | 3.93% | +21 bps | 8% |
| No inclusionary set-aside | 3.93% | +22 bps | 8% |
| Full zoning package | 4.37% | +66 bps | 24% |
| Property tax to zero | 4.32% | +60 bps | 22% |
| Rent +10% | 4.25% | +53 bps | 19% |
Components do not sum to the package. Levers interact.
Entitlement is the weakest lever by an order of magnitude. Ten months of carry on $2.4 million of land is $160,000, or 1 percent of cost.
6. Breakevens
What each input would need to be, alone, to hit 6.50 percent:
| Input | Base | Breakeven | Move |
|---|---|---|---|
| Average rent | $2,450 | $3,726 | +52% |
| Hard cost / SF | $275 | $119 | −57% |
| Land | $2.4M | −$2.96M | n/a |
Under the full zoning package, residual land value is still −$1.48 million. The deal fails at any land price, so land drops out of the argument.
7. Sensitivity
Value minus cost, $ millions.
| Cap rate ↓ / Rent → | $2,205 (−10%) | $2,450 | $2,695 (+10%) |
|---|---|---|---|
| 4.75% | −5.5 | −3.7 | −1.9 |
| 5.25% | −6.4 | −4.8 | −3.1 |
| 5.75% | −7.2 | −5.6 | −4.1 |
No cell clears zero.
Pro Forma Calculator
40-Unit Apartment Building, Washington, D.C.
Every input below carries a source. Drag any slider to test the model against a different assumption.
The building
What it costs
Return on cost
3.72%
Earns3.72%
Needs6.50%
- Total development cost
- $16,328,290
- Of which, entitlement carry (land only)
- $224,000
- Of which, construction carry (avg. draw)
- $775,715
- Effective gross income
- $1,085,109
- Property tax (solved iteratively)
- $98,253
- Stabilized annual NOI
- $606,856
- Implied stabilized value
- $11,559,166
- Value minus cost to build
- -$4,769,124
8. Inputs and sources
Every input carries a status:
- Verified. Taken directly from a published source.
- Verified range. The source gives a range. We picked a point inside it.
- Derived. Calculated from published figures.
- Estimate. Our judgment, flagged for checking.
- Assumption. A modeling choice.
| Input | Value | Status | Source |
|---|---|---|---|
| Units | 40 | Assumption | |
| Unit mix and rents | 10 studio / 22 one-bed / 8 two-bed | Verified | RentCafe |
| Efficiency (rentable ÷ total) | 80% | Estimate | D.C. Policy Center |
| Land | $2,400,000 | Estimate | LoopNet |
| Construction cost per sq ft | $275 | Verified range | RLB Q1 2026 |
| Parking spaces per unit | 0.50 | Estimate | D.C. Policy Center |
| Cost per parking space | $35,000 | Verified | D.C. Policy Center |
| Fees and design | 20% | Estimate | |
| Approval timeline | 14 months | Estimate | D.C. Department of Buildings |
| Construction timeline | 18 months | Estimate | |
| Construction loan rate | 8.00% | Verified range | CLS CRE |
| Average rent | $2,450 / month | Verified | RentCafe |
| Affordable-unit share | 10% | Verified | D.C. Policy Center |
| Affordable-unit rent | $1,550 / month | Estimate | DHCD 2026 schedule |
| Empty units and unpaid rent | 7% | Derived | Yardi Matrix |
| Other income | 3% | Estimate | |
| Running costs per unit | $9,500 / year | Estimate | |
| Property tax rate | 0.85% | Verified | D.C. Office of Tax and Revenue |
| Cap rate | 5.25% | Verified range | CBRE H1 2026 |
| Risk premium for building new | 1.25% | Estimate |
Other sources
- Permits by year: U.S. Census Bureau Building Permits Survey via FRED
- Zoning share, appeals and appeal delays: D.C. Policy Center
- Permit review times: D.C. Department of Buildings
What we’re checking next
These estimates are being checked against real project data from a D.C.-area construction firm:
- Fees and design percentage
- Approval timeline
- Construction timeline
- Running costs per unit
Land is not on the list. The building fails even with free land, so the land estimate doesn’t change the conclusion.
Reproduce it
The full model is a standalone Python script. Same inputs, same outputs as the calculator. Download dc-model.py
How the model works: Method →